Alco Living was appointed by Berkeley Homes to deliver the supply and installation of kitchens for Blocks B and C at Eden Grove, a major build to rent development on London Road in Staines-upon-Thames.
The wider scheme comprises six residential blocks, built and handed over in phases. Working across two blocks on overlapping programmes, Alco Living's role is to provide a complete and well-coordinated kitchen package that supports Berkeley Homes' build programme and customer handovers, from first installation through to final finishing and aftercare.
Berkeley Homes required a dependable delivery partner to complete the 158 kitchens across Blocks B and C, with works resuming under a revised agreement.
The package covered kitchen installations, appliances, worktops and second fix finishing, alongside concierge kitchen works, welfare upgrades and stone trim detailing.
With the development delivered in phases, installations needed to align closely with the main build programme and staggered handover dates. The brief also called for flexibility to client-agreed specification changes, while maintaining a consistent standard of finish across every home.
Alco Living adopted a coordinated, programme-led approach, working closely with Berkeley Homes' commercial and site management teams throughout.
Works were sequenced block by block and plot by plot, in line with construction progress and planned handover dates. With Blocks B and C running on overlapping programmes, resources were planned carefully to maintain momentum on both without compromising quality.
Site access was managed through regular communication with the site management team, ensuring installers, materials and deliveries arrived where and when they were needed within a busy, phased site.
Quality inspections at each stage of installation helped identify and resolve issues early, reducing return visits and supporting smooth handovers. Health and safety remained a priority throughout, reflecting the demands of a live construction environment.
Works on Block B began in February 2026, followed by Block C in March 2026, with both programmes progressing in parallel.
Beyond the individual apartments, Alco Living delivered kitchen works within the concierge area, together with welfare upgrades supporting the site. Stone trim works were also completed, providing a clean and consistent finish.
As sections of the development reach completion, Alco Living continues to carry out remedial and finishing works, ensuring each plot is ready for customer handover.
All kitchens have been fitted across the plots in Blocks B and C, meeting the client's objectives for the package and supporting the continued progress of the wider Eden Grove development.
Close coordination with Berkeley Homes' teams has allowed installations, remedial works and customer requirements to be managed alongside the phased handover programme, helping keep homes on track for occupation.
The completed kitchens provide a consistent, high-quality finish across both blocks, contributing to the overall appeal of the development for new residents.